Boeing now says it expects 737 MAX to resume commercial service in January

This post was originally published on this site

© Reuters. FILE PHOTO: An aerial photo shows Boeing 737 MAX aircraft at Boeing facilities at the Grant County International Airport in Moses Lake© Reuters. FILE PHOTO: An aerial photo shows Boeing 737 MAX aircraft at Boeing facilities at the Grant County International Airport in Moses Lake

By David Shepardson

WASHINGTON (Reuters) – Boeing (NYSE:) Co said Monday it now expects its grounded 737 MAX to resume commercial service in January as it works to address questions from regulators over its documentation for revisions to the plane’s software.

Boeing said it is possible that resumption of MAX deliveries to airline customers could begin in December and added it is working toward final validation of the updated training requirements “which must occur before the MAX returns to commercial service, and which we now expect to begin in January.”

American Airlines (NASDAQ:) and Southwest Airlines (NYSE:) said Friday they were pushing back the resumption of flights because of the 737 MAX grounding until early March.

Last week, Reuters reported that U.S. and European regulators had not been able to complete a software documentation audit in Cedar Rapids, Iowa of the 737 MAX because of significant gaps and substandard documents. The U.S. Federal Aviation Administration (FAA) must complete that audit before a key certification test flight can be scheduled.

“We are taking the time to answer all of their questions,” Boeing said in a statement Monday, adding that it is aiming for “FAA certification of the MAX flight control software updates during this quarter.”

Boeing also said that it has completed one of five milestones needed before the plane can return to service: a multi-day eCab simulator evaluation with the FAA to ensure the software system performs as intended even if there is a system failure.

On Friday, the FAA told U.S. lawmakers a preliminary review by a blue-ribbon panel has found Boeing’s design changes to a key safety system to be “safe” and compliant with regulations.

The FAA did not immediately comment on Monday but has said it will need 30 days from the time of the certification flight before it could unground the plane.

Disclaimer: Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. All CFDs (stocks, indexes, futures) and Forex prices are not provided by exchanges but rather by market makers, and so prices may not be accurate and may differ from the actual market price, meaning prices are indicative and not appropriate for trading purposes. Therefore Fusion Media doesn`t bear any responsibility for any trading losses you might incur as a result of using this data.

Fusion Media or anyone involved with Fusion Media will not accept any liability for loss or damage as a result of reliance on the information including data, quotes, charts and buy/sell signals contained within this website. Please be fully informed regarding the risks and costs associated with trading the financial markets, it is one of the riskiest investment forms possible.