Exclusive: Boeing delays plans for record 737 production until 2021 – sources

This post was originally published on this site

© Reuters. FILE PHOTO: Aerial photos show Boeing 737 Max airplanes on the tarmac in Seattle© Reuters. FILE PHOTO: Aerial photos show Boeing 737 Max airplanes on the tarmac in Seattle

By Eric M. Johnson and Tim Hepher

SEATTLE/PARIS (Reuters) – Boeing Co (N:) has delayed plans to reach a record production rate of 57 737 jets per month next year, industry sources said on Thursday, even before the U.S. FAA announced a new delay in the 737 MAX return to service that raised uncertainty over production plans.

The world’s largest planemaker has also delayed plans to step up from the current rate of 42 jets per month to 46 jets this year until March 2020, as the company struggles to win regulatory approvals for its best-selling jet after deadly crashes.

The U.S. Federal Aviation Administration said on Wednesday that the agency will not approve the grounded commercial jet for flight before year end, and said it was investigating production issues at the factory in Renton, Washington.

FAA chief Steve Dickson, who met with Boeing Chief Executive Dennis Muilenburg on Thursday, is concerned the U.S. airplane maker is pursuing a 737 MAX return-to-service schedule that is “not realistic,” according to an email seen by Reuters.

A Boeing spokesman did not immediately respond to a request for comment.

In October, Muilenburg told analysts Boeing expects to be able to maintain its current monthly production rate of 42 aircraft, followed by incremental rate increases that would bring the production rate to 57 in late 2020.

Industry sources said this plan has been delayed by months.

After getting to 47 jets monthly in March 2020, Boeing will make its next increase to 52 jets per month in September 2020, according to one person familiar with the plans. It will then not reach a record stride of 57 per month until April 2021, the person and a second industry source said.

A third industry source confirmed the general timeline but cautioned the plan could be further delayed by the 737 MAX approval process.

Boeing mainly builds the latest version of its cash-cow single-aisle family at its Seattle-area factory, but also builds a small number of earlier or military variants of the 737.

In April, Boeing cut the number of 737s it produces monthly to 42 from 52 after halting deliveries to airline customers, cutting off a key source of cash and hitting margins.

Because the grounding happened when Boeing was going up towards record production levels, and each move of the sprawling supply chain has to be planned far in advance, Boeing and its suppliers are now caught between two conflicting pressures: preparing to get back on the upward path as soon as the plane is flying but also ratcheting downwards if regulators stall and the grounding continues for longer than expected.

Disclaimer: Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. All CFDs (stocks, indexes, futures) and Forex prices are not provided by exchanges but rather by market makers, and so prices may not be accurate and may differ from the actual market price, meaning prices are indicative and not appropriate for trading purposes. Therefore Fusion Media doesn`t bear any responsibility for any trading losses you might incur as a result of using this data.

Fusion Media or anyone involved with Fusion Media will not accept any liability for loss or damage as a result of reliance on the information including data, quotes, charts and buy/sell signals contained within this website. Please be fully informed regarding the risks and costs associated with trading the financial markets, it is one of the riskiest investment forms possible.